[P6 Client] Why planned values for comparision are different from each graphs?

edited Oct 27, 2013 3:50PM in Primavera (MOSC) 4 commentsAnswered
Hi all,

Would you advice me why P6 client's graphs have following differnces?
I think it comes from P6's design philosophy or something, but I couldn't reach it.
Kindly refer to attachment.

Planned/Budgeted values which can be selected in following graphs
-- Activities view, Activity Usage Profile --> Baseline and Budgeted
-- Tracking view, Project Gannt/Profile Layout --> Baseline (Budget cannot be selected)
-- Activities view, Resource Usage Profile --> Budgeted (Baseline cannot be selected)
-- Tracking view, Resource Analysis Layout  --> Budgeted (Baseline cannot be selected)

Any advice would be appliciated.

Best regards,
Kenichi Kaneko

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center