Hi all,

We have faced an issue in R12.1.3 when releasing Planned orders and changing the date for intercompany process (soource organization another Inventory Organization).

Issue is that the Need By Date in the Internal Requisition in ERP is not according to the date entered in ASCP. I have seen even the Need By date in the past, not following any logic in my opinion.

Has someone faced this issue before?