Planned labour usage
To provide resource profiles, I do what most people do and export the early and late resource usage profiles int Excel. Since i do not want to spend on either the early or late dates I use a formulae in Excel to provide planned values.
For the purposes of this discussion these values are the mid point of the early and late dates. How can I get P6 to provide these planned dates and also the associated time phased resource values.
Best regards
Rob Gray