MFG item lead time,PO lead times not reflecting in ASCP output
Created FG Item:
Processing lead time: 2
Created Component for the above FG:
Processing lead Time:3
post processing lead time: 1
No planning time fence
ATP indefinite supply days >120
Plan options >Main > Material scheduling method > Order start date
Created forcast for FG on D14 for 20 Qty.
I am expecting :
Planned order(WIP Job) suggestion date for FG to be D14 - 2 days
And Component planned order(PO) suggestion date for FG to be D14 - 2 days - 4 days
But i am getting suggestion date as D14 for both FG and Component.
Please suggest.
Thanks.