OSP with Discrete Job
We are trying to setup OSP for an item that will have 2 OSP Resources attached to the Routing. PR is creating after the WIP move to the 1st OSP step, but not for the 2nd OSP step.
Here is the setup and example:
FG item=123456 (this goes to Supplier X)
OSP item=234567-OSP (is Resourced from Supplier X)
OSP item=345678-OSP (is Resourced from Supplier Y)
Routing:
10=Internal Production
20=Internal Production
30=Internal Production
40=OSP Supplier X
50=Internal Production
60=OSP Supplier Y
Step 1. Discrete Job is created for 123456
Step 2. WIP Move
Step 3. WIP Move
Step 4. WIP Move to (1st OSP Step)