Hi to all
currently we are using standard costs 07 for all our items

we use a mix of configurated and standard products, at all manufacturing stages (prime materials, semi elaborated and end items)

I have been reading about weighted average cost method 02, and have several questions.

1. If you use cost method 02 for prime materials, you never have to simulate and freeze those items at cost method 02?

2. If you use cost method 02 for standard semi elaborated or end items, how and when is the new weighted average cost of this semi elaborated or end items calculated?

3. do you need to simulate and freeze cost method 02 for standard semi elaborated or end items?, how this combine with changing costs at manufacturing?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center