Actual Cost & Units are not automatically getting updated after assign Resource curve
As I don't want the cost to be spread Linear , I assigned resource curve to all my assigned Resource .
While updating the activities I have following issue .when the activity status is in Progress
1.Actual Cost is not getting updated.
2.Actual Unit is not Getting Updated.
3.Unit % Complete is not getting updated.
4.Earned Value is showing irrelevant Data.
5.At Completion Cost is not equal to budgeted total cost
6.At Completion unit is showing Irrerelevant data
In my Project Setting - Calculation Tab
Link Budget & At completion for non started activity is ticked
Resource Setting
Auto Compute actual - Ticked