Create "Start No Earlier Than" Constraint
I have a task that I want to have its proposed start based on another task - 2 days, but I don't want to push the other task If this task is late.
As you can see in this image, I want the QA task to be tied to the date the package will be reviewed -2 days. If the QA task doesn't get done before the review, it should not push the date for the review activity, nor any activity after it. Is this possible?