Tool Fixture Scheduling in E1
has any one implemented/used tool/fixture scheduling in E1? I've 3 work centers in textile as knitting machines with different diameters 15", 17" & 19". Each of this work center can be used with intergchange tooling of 84, 96, 108 Needle counts. Each machine has capability to work with different tooling.
However to ramp up my capacity for over a period of time. I keep changing my machines capacity by switching toolings.
Date To Date From WC Machine Tooling Needle count
18/11 23/11 15" 1 84
18/11 23/11 17" 1 96
18/11 23/11 19" 1 108
25/11 30/11 15" 2 84- Increase capacity of 15" by adding 1 more machine and use 84 tooling on 19" machine
25/11 30/11 17" 1 96
25/11 30/11 19" 0 108- Use this for 15" machine to add capacity
Can anyone share idea/document to use Tool scheduling in E1? So that we can schedule tooling for the future periods in order to calculate capacity for upcoming demand.