Hello Gurus,

I create a make Item End Assembly, with a Processing (Manufacturing) Lead Time of 5, and I entered a Forecast of 10 for 25-Nov-2013.

After the MRP completed, It suggested a Planned Order Due Date of 25-Nov-2013. I then Released it to create a new Work Order which was successfull.

However, I do not understand why the Discrete Job Start Date is 25-Nov-2013.

I was expecting the Discrete Job Start Date to be 20-Nov-2013 to take into consideration my 5 days lead time (which is 25-Nov-2013 - 5 days) 

Let me know if I am missing something or which setup I should be looking at.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center