MRP Workbench - Manufacuring Item (End Assembly) Discrete Job does not consider the Processing Lead
I create a make Item End Assembly, with a Processing (Manufacturing) Lead Time of 5, and I entered a Forecast of 10 for 25-Nov-2013.
After the MRP completed, It suggested a Planned Order Due Date of 25-Nov-2013. I then Released it to create a new Work Order which was successfull.
However, I do not understand why the Discrete Job Start Date is 25-Nov-2013.
I was expecting the Discrete Job Start Date to be 20-Nov-2013 to take into consideration my 5 days lead time (which is 25-Nov-2013 - 5 days)
Let me know if I am missing something or which setup I should be looking at.