ATP Scheduling
Hi,Have few queries related to ATP(based on ASCP Plan output) scheduling.
1) Can we make the scheduling priority to be given based on ordered date?
In Scheduling priority, i am seeing only based on request date and schedule ship date.
Scenario is:
SO A:
Order date: D0
Request ship date: D5
SO B:
Order date: D1
Request ship date: D5
Now the priority should go to SO B.
2) And time stamp can be taken in to consideration while scheduling? Suppose if we schedule order B with Request date D5-11:30:30 and schedule order A with Request date D5-11:35:30.