EVM Graph not appearing for a Program
Hi,
I am not able to see the EVM graph for a program -100738. But I could able to see the EVM graphs for individula child projects.
I followed the following steps.
1. Linked the chld projects to program.
2. Base lined the Work Plan.
3. Entered the Financial Budgets
4. Base lined the Financial Budget.
5. Entered the Percentage completion to all Child and Program at task level.
6. Ran the Update and Process programs as per the sequence given below.
a)PRC: Update Project Summary Amounts
b)PRC: Refresh Project Summary Amounts
c)PRC: Refresh Transaction Summary Amounts
d)PRC: Load Project and Resource Base Summaries
I am not able to see the EVM graph for a program -100738. But I could able to see the EVM graphs for individula child projects.
I followed the following steps.
1. Linked the chld projects to program.
2. Base lined the Work Plan.
3. Entered the Financial Budgets
4. Base lined the Financial Budget.
5. Entered the Percentage completion to all Child and Program at task level.
6. Ran the Update and Process programs as per the sequence given below.
a)PRC: Update Project Summary Amounts
b)PRC: Refresh Project Summary Amounts
c)PRC: Refresh Transaction Summary Amounts
d)PRC: Load Project and Resource Base Summaries
0