When PR using AME to submit for approval , is forward checkbox enable or disable ?
ct folllow Forward To Check Box Is Disabled In Requisition Screen for a Returned Req approved with AME (Doc ID 1564695.1)
apply Patch <16879227:R12.PO.B>. after that he found that
When PR using AME to submit for approval , forward checkbox is disable / greyed .
so I wonder if it is internded behavior that this patch disable the forward checkbox.
in my test , before apply patch 16879227 ,
( POXRQERQ.fmb 120.43.12010000.14 , POXAPAPC.pld 120.18.12010000.8 )
When PR using AME to submit for approval , forward is enable
after apply patch 16879227 ,
( POXRQERQ.fmb 120.43.12010000.41 , POXAPAPC.pld 120.18.12010000.40 )
When PR using AME to submit for approval , forward is disable.
Thank you