WBS Path Lost / Activities not Copying with Project

edited Nov 11, 2014 7:36AM in Primavera (MOSC) 15 commentsAnswered
A user is currently experiencing some major issues with her Baseline schedule (and there is no backup).  Any input is appreciated.

Her WBS Path has been lost - all WBS is down to 1 level. On the WBS page,  under the "WBS Path" for each WBS is a single digit instead of the decimals.

Also, while troubleshooting - when we copy/paste the schedule, the activities are not copy/pasting with the schedule.  We copy/paste with all the boxes checked, open the new project and no activities are displayed.  No filter.

Again, please help. Any input into what might have happened, or how we can fix this would be appreciated.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center