Issues with updating baseline and assigning resource by role (results in duplications of resources)
Resourece Role Budgeted labor units
Bob Plumber 8 hrs
I later find out that Bob is no longer working this activity and Jan will be doing that work. I want to update the baseline to reflect the change. I proceed to change the activity and it looks like the following:
Resource Role Budgeted Labor Units
Jan Plumber 8 hrs
After going through all of the steps to update the baseline I see that the planned value labor units shows 12 hrs....After restoring the basline, I locate the activty that was changed it looks like the following: