Production Cost is wrong when a batch belongs two periods and has wip completion return
Hi all,
Now, we have one problem, my cost type = PMAC . I give you one example:
- A batch :
+ Ingredient issue: 29-nov-13
+ wip completion : 30-nov-13, quantity = 10
+ wip completion return : 30-nov-13, quantity = 10
+ wip completion : 01-dec-13 quantity = 10
+ close batch
when running actual cost process, the system yields all ingredient consumption amount for product in nov-13, and ingredient consumption amount for product = 0 in dec-13
If there' anyone else got the issue the same and having solution, please help me !!!
Thanks,
Alice
0