Resource Calendar is not working Primavera P6 version 7.0
I hope a can get help. There is one activity has 7 days calendar, but its resources has only 5 days availability, when i open "Assignment" tab i notice that resources has still 7 days assignment. it should display "0" on Saturdays and Sundays but it doesn't. please help
0