Resource Calendar is not working Primavera P6 version 7.0

edited Dec 27, 2013 5:02AM in Primavera (MOSC) 3 commentsAnswered
I hope a can get help. There is one activity has 7 days calendar, but its resources has only 5 days availability, when i open "Assignment" tab i notice that resources has still 7 days assignment. it should display "0" on Saturdays and Sundays but it doesn't. please help