Peoplesoft - Project Costing - processing status issues
Wonder if someone can assist.....looking for some research material on Project Costing processing statuses....have a user who has closed projects, yet the processing status is still 'pending;.
Everything looks ok effective sequence wise - ie change from active to close happened same day, and active seq is 0, and close sequence is 1.
I have a workaround for the test environment - and re-activating and closing again on same day with increment sequence numbers seems to work - but was looking for ideas on causation ?