Past Due Sales Orders show suggested due date earlier than plan run date
We have noticed that if the ASCP plan is run say today 7-jan-2014 and there are past due sales orders(schedule ship date say in dec-2013) the suggested due date of these sales orders after the plan has completed shows as 6-jan-2014 23:59:00 .
On the other hand if there is a WO for the same part which is past due ,its suggested due date is moved to plan run date and shows as 7-jan-2014
.Is this expcted behavior for past due sales orders to have a suggestd due date as in the example above?If so what is the explanation for this?