Late supply pegged to sales order exception :planned order created fter demand due date

edited Jan 22, 2014 12:53PM in Value Chain Planning - EBS (MOSC) 2 commentsAnswered
We are on 12.1.3 and use unconstrained planning.Items have no demand or planning time fences yet in some case we are noticing that as an example if item A has say a work order demand for 9-jan-2014 , it is creating a planned order for 15-mar-2014 for item A  and issuing a Late supply pegged to sales order exception .The work order demand is qty 1 and the planned order is also qty 1 and is pegged to only this work order demand and no other demand.since we have no time fences at all and the planned order is pegged