edited May 22, 2014 12:00PM in Projects - EBS (MOSC) 9 commentsAnswered
 Hello,
I have an issue on a project where a resource's ETC cost is being calculated using his previous job rate.

For example, an employee had a job where the rate was 26. 26 * overhead * fringe = 55.38. This was his old burdened rate yet it is still being calculated for future months (ETCs) on the project.

He is now in a job that has a rate of 40. 40 * overhead * fringe = 85.20. This is not being calculated for the ETCs but should be.

One thing to note - he did have a job change at some point during the duration of the project. But regardless, the ETCs should now be factoring in his current job rate rather than his old one.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center