R12 : Raising Future Requisitions and GL Date ?
We are planning to use procument functionality to capture future Requisitions and Encumberances both obligation and commitments.
Raising Future Requisitons single or multiple periods
1. The requisitions shows GL date, which defaults to current date and we change it to the period the line belongs, for example, Three Line requisition , we will choose Feb, March April 2014 periods.
2. When the Requisition review Page is shown , we see the three lines but do not see the GL Dates information of the Line
3. When the requisition is submitted for Approval, Approver can see three lines but do not see the GL Dates information of the Line