Inconsistency in scheduled dates.

edited Jan 14, 2014 2:19AM in Primavera (MOSC) 1 commentAnswered
Hi There

We are facing some problems while updating Primavera progress for a Project,

Request you if anyone can help to correct it out:

1) Early Finish date of Completed Activities (Completed in Sept-13 to Dec-13) is driving one of the Engineering Milestone to Apr-14, which is in Feb-14 as per Baseline.
(Technically, Early and Late dates of Completed Activities should not have any relevance and,
ONLY activities "In Progress" or "not started" should drive the logic for that milestone,
We would like to know why Completed activities have impact on finish date of milestone and how can we correct it)

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center