Hi ,
We have a problem with ASCP . The plans are showing "Reqeusted ship date" to a date way in the future. I am not sure, where this is being picked up. We have a 2 db arch,
1 for EBS and 1 for APS. There are db links to and from each other. Can you please let me know how to resolve this issue. I am attaching the screen shots.
Please advise,
Thanks
Ram
We have a problem with ASCP . The plans are showing "Reqeusted ship date" to a date way in the future. I am not sure, where this is being picked up. We have a 2 db arch,
1 for EBS and 1 for APS. There are db links to and from each other. Can you please let me know how to resolve this issue. I am attaching the screen shots.
Please advise,
Thanks
Ram