 Hi,
I notice one thing when I export my project to MSP containing only two milestones (Finish milestones) linked together by SF relationship.
When I opened this project in MSP I was able to see my milestones but without relationships. I'm aware that there is some problem with moving milestones from P6 to MSP but even in KB I couldn't find any article decribe this issue.
Can I count on Your help? Any Advice? P6 and MSP projects attached. Remove .jpg extension from the end of file name.

P6 8.3.1
MSP 2010