Activity won't start on Sunday
Hi! I have a 7 day calendar assigned to my activity, I checked the calendar settings and it is working Sunday-Saturday 8hrs per day but for some reason when I assign the calendar to an activity the activity won't start on Sunday. When I change the logic it just bounces from starting on Monday to Saturday and vice versa. Is there any setting in P6 that would prevent an activity from starting on a Sunday? There is no holiday on the calendar, no constraint on the activity and it is task dependent. Please let me know if you have any suggestions.