PS 9.2 EDI orders- Freight issue
Hi,
We are having issues related to freight charges in PS 9.2 when we process EDI orders.
As per Peoplebooks, when we have EDI orders, we run Order Completion process that generates Deliveries. Then for third party freight provider, the process sends and asynchronous message for Freight request.
The Freight Status in IN_DELIVERY table is changed to Rate Requested.
When a response is received, we need to run the Fulfillment Request process (IN_FUL_BCT) to populate the freight.
However, our scenario is different from the above. We already have freight charges with us for every order at the time of EDI load and want that Order completion process uses that freight charge while creating Deliveries.