Hi,

in the document "E1: 31: How Work Order Start Date is Calculated for Variable Lead Time (Doc ID 881632.1) I have read that the start date is calculate using this formula:

 (LTPU.F4102 X UORG.F4801)/ TBC.F4102 + SETL.F4102 + QUED.F4102

                     Work Hours per day from Mfg. constants (F3009)


Where LTPU: Lead time per unit from Item Branch table
           TBC: Time basis code from Item Branch table
          SETL: Set-up Hours from Item Branch table

         QUED: Queue hours from Item Branch table 


I use JDE 9.1 and I'm sure that the system doesn't use the field LTPU because I have change the value in the field LTPU a lot of time  and the work order start date is always the same.

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center