Asset not generating PM Work Orders since October 2013
This is what I looked at so far and have found no reason for the PM to have stopped generating.
Assets> View Asset Number> query the asset - everything looked good - The asset was active and maintainable
Activity> Activity Workbench> enter Asset EBF-S8> Launch> Results> Asset with Activities> EBF-S8 -- 14 Activities listed for this asset
Activity> Organization Activities (Activities have Long Text Attachments) Total of 14 active Activities for this asset