I have P6 EPPM 8.3 - I need to know what are you using instead of Methodology Management (Project Architect) functionalities.
We create a lot of projects for Planning Department and modify their costs of the Phases (WBS) as a percentage of the total cost of the project. Is there any functionality that can help me to do this with 8.3?
Thanks!