PRC: Distribute labor costs program showing up "Missing Cost Rate" rejection reason

edited Jun 18, 2018 3:36AM in Projects - EBS (MOSC) 6 commentsAnswered

Hi Experts,

One of our clients had run the "PRC: Distribute Labor Costs" program, the output of which is showing up a rejection reason as "Missing Cost Rate." I have queried the employee in the cost rate schedules and found that he had a rate defined.

Please suggest where else can I check and fix this issue.