Task Flow Scheduler Issue Cross Over Days
HFM Version 11.1.2.2.306
We have been using the task flow scheduler with success in synchronizing data between HFM and Planning.
The one glitch that we have found is that any jobs scheduled for the next day do not execute. In other words, jobs run all day long but as soon as we cross over into the 12 01 AM of the next day, the jobs will not run. We have to re-schedule them.
Has anyone experienced this bug or found a resolution?
Thanks,
Greg