P3112 Date calculation with queue hours on identical work centers
I am trying to figure out how the date calculation works in manufacturing. So far, when no queue hours are defined it works as expected and what I can find in the documents about calculation dates. But when I define queue hours on the routing steps, I cannot explain the dates calculated anymore.
Item A - MFG leadtime quantity 48
Four routing steps:
OPSQ | WC | Queue | Setup | Mach | Labor | Move |
1 | w103 | 1 | 2 | |||
2 | w173 | 4 | 1 | 2 | ||
3 | w152 | 4 | 1 | 6 | ||
4 | w152 | 4 | 1 | 6 |
Three work orders:
WO | Item No | Qty | UoM | Start Date | Request Date |
195062 | 205.837.001 | 60 | EA | 17-2-2014 | 21-2-2014 |
195938 | 205.837.001 | 48 | EA | 18-2-2014 | 21-2-2014 |
195939 | 205.837.001 | 24 | EA | 18-2-2014 | 21-2-2014 |