Mapping Client Requirement on Forecast Creation
Hi Experts,
We have client requirement as follows(MRP, 12.1.3)
1.Client having two plan ie a.Monthly Plan and b.Weekly Plan
The monthly plan:
1+3 is the forecast method client following. 1+3 is nothing but 1 month Firmed plan and 3 month forecast so total plan is for 4 month( Need to Entered in System to Generate Component Requirement(Buy item))
Weekly Plan:
Every Thursday weekly plan generated for next week ie Week start day is on Sunday and plan for Sunday generated on Thursday(Need to enter in system to generate Job Order and Variation Buy Item requirement)
Example:
Item "X" has monthly plan Qty say 5000 Mtr and it will be entered every week as W1 1500 Mtr, W2 2000 Mtr, W3 no plan and W4 2500 now