Hi All,

We are using cost type PMAC for our Inventory valuation.

In our Formula, Product tab has two lines as Primary Product (line1) and Secondary Product (line2).

Primary product is 100% quality approved.

Secondary product has some quality defect which needs to be reprocessed.

My requirement is, I need to contribute my ingredients and resources cost to primary product if batch approved 100%. At the same time if batch rejected for quality defects, then I need to allocate only material cost, not the resource costs. How we can map this?. Kindly share your knowledge on this.

Now, I set cost allocation factor 1 for line1 (primary product).

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center