START_FORECAST_DATE how to influence it to start from march 2014 instead of Aug 2014?
Hi All,
We have scnearios where the Shipment history (based upon Request Date) is collected to a future date say (7/27/2014). We are observing that the Analytical Engine is proving forecast "start_forecast_date" is from (8/3/2014).
We would like the stat engine to provide forecast from (03/02/2014) itself. In our business we have cases where the shipments are done for future dates.
Will setting the Engine Parameter?Date / "Last_date_backup" to 03/02/14 -- influence the ingine to start forecasting from t03/02/2014 ..instead of 8/3/2014.
Is that all the chages required to achived this behaviour ? Please advice.