We have come across a strange issue while using Suppression and was wondering if anyone else has noticed this issue (if so, do you have a fix). Otherwise, I believe we will be opening an SR.

Example: We have a Filling Line that has two activities set up against it. One is Bi-Annual and One is Annual. The Annual activity is set up to suppress the Bi-Annual one.

When it comes time for these Work Orders to be generated, the Annual Work Order is created, and the Bi-Annual Work Order is suppressed (so far, it is working as it should).