The true meaning of BL Completed; In Progress and Not Started Activities
Hi All,
Take a look at http://docs.oracle.com/cd/E25030_01/English/User_Guides/p6_data_dictionary.pdf
Look at document page number 41, for the meaning of "BL Completed Activities".
I Quote: The number of completed activities in the project baseline.
:
It makes sense, if I interpret myself, this column shows the total number of activities in the BL Project Schedule (that at the time of base-lining), had the status of 'Complete'. However, I think we have been mislead. Doing a test it leads me to believe it's actually calculated as :
The total number of activities THAT SHOULD have the status 'Complete' as of the Data Date...