Primavera (MOSC)

MOSC Banner

Resource assignment question

edited Aug 14, 2014 8:28PM in Primavera (MOSC) 3 commentsAnswered


Hi! I have a schedule where the resource assignment is not matching up with the activity. The resource is assigned to a level of effort activity, the activity is finishing in May but the resource assignment finishes in March. The relationships are set to SS and FF. It is a material resource with max units/time =1/d and a rate of $0.00. When I remove the resource and re add it to the activity it correctly calculates the resource assignment. Any suggestions as to why the resource assignment is not calculating the same finish as the activity to begin with?

Thank you!!

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center