MSP import issues with material res assignments in P6 EPPM V8.3?

edited Mar 18, 2014 12:00PM in Primavera (MOSC) 1 commentAnswered

Are there any know issues with importing of MS Project with tasks having assignments of material type of resources in P6 Web version 8.3??? Here is what I am experiencing..........

1. In V8.3 Web version (EPPM), I could import MS Project (created in MSP 2010) with 600 tasks, many levels and complex dependencies.

2. After I loaded the MSP project with labor and material types of resource assignments, import failed. Log file did not point specifically to any error.

3. To narrow down the issue, I deleted assignments of all material type of resources and the import was successful

4. Then I added just one material resource assignment and it was again failed with no specific message in log file.

Tagged:

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center