Discount did not flow to Projects when the distribution was changed after payment. Why?
We have updated the distribution lines in Payables on four invoices where the project was not included but it needed a project. The invoice line amount made it to Projects and GL but the discount only went to GL and not to Projects.
In PRC:Interface Supplier Cost we have "Interface AP Discount" = Y and it does bring in the discount but not when distribution was changed after payment.
Is this a bug? Or are we missing something? We are on Oracle EBS 12.1.3 and patch set R12.PA.B.3 for Projects and R12.AP.B.3 for Payables.