migrating codes from P6 V6.2.1 into P6 V8.3

edited Mar 20, 2014 12:00PM in Primavera (MOSC) 2 commentsAnswered

does anyone know how to migrate all of our codes from the projects residing in P6 6.21 into the 8.3 version?  when we import the project via an XER file, none of the activity codes, (Global, EPS and Project codes) along with user defined codes are importing into 8.3.  is there an Admin Rights restriction on codes?  We found that resources would not import into 8.3 until we were reset as a <Super User>