Master Schedule in P6
What is the proper way to create a master schedule, which includes multiple projects all with different start dates, finish dates and total duration. We have one on file which has enormous Total Float, when i click on the project tab, it appears that it has start date, finish date and duration of the project with the longest duration and that the total float is being calculated as if the other projects where under this particular project.