The corrected hours for same activity, will the actuals get added or overwritten?
Hi Guys,
User facing this scenario
- submitted a timesheet against Timesheet Test 2 activity with 25hours
- Approve Timesheet
- Apply Actuals and store performance
- Reject the timesheet
- correct the timesheet and move hours from Test 2 to Test 3 and resubmit
- Approve the timesheet with the corrections made
- Apply Actuals to the plan as previous
And User says that the hours are not correcting, they are adding to the new task which the resource has resubmitted with, but they are also staying on the old task??
This should not be happening
Please let me know if the actuals will be over written or added to previous ones..?