Primavera (MOSC)

MOSC Banner

Actual Labor Units reset to 0 after calculating schedule

edited Apr 3, 2014 12:00PM in Primavera (MOSC) 1 commentAnswered

After I calculate the schedule a few of my activities' Actual Labor Units reset to Zero even though I have typed in the actual hours.  My %  Complete type is Physical and my Duration type is Fixed Duration & Units for all activities.  None of the other activites do this.  Any ideas?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center