PO commitment - needs hit PA ledger type after approval status (230 last to 280 next)

edited Apr 18, 2017 5:51PM in Distribution - JDE1 (MOSC) 5 commentsAnswered

Hello

I have a question related to WHEN an order should create a commitment.

Is there a setting somewhere that will say - At the time an OP order is approved, it will create the commitment (hit PA ledger).  Currently the commitment is created at the CREATE OP Status (220 last to 230 next order status ).  We would like to see an order commit at the 230 last to 280 next status.

Is this possible???

Any guidance greatly appreciated!

Best regards,

MD'Angelo