Supplier calendar is not honoured by ASCP Collections
Hi
We are in EBS 12.1.3. Here are the details on our issue
1. We are using Global ASL with Supplier capacity calendar setup in Planning Constraints> Supplier Capacity Calendar.
2. Profile MSC: Buy Order Processing Lead Time Calendar is set up with Supplier Capacity Calendar.
3. We have set up the Suppler Capacity calendar with Exception dates say Supplier is closed for 2 Months.
4. Ran the ASCP Collection , but the suggested due dates in ASCP is not honouring the Supplier closure dates as set up in the supplier calendar.
Any help in this issue is appreciated.
Regards
Jagan