Question on Oracle Burden schedule
We use burden schedules for cost+ projects. But we have a problem when updating existing burden rates.
Demostration:
Expenditure item id : 1234
Expenditure date : Jan 2014
Expenditure status : posted to GL
raw cost : 100 $
Burden %: 15%
Burdened cost : 115 $
On Feb 1 2014, when I change the burden % to 20% , then all expenditure item ids are recalculated including the ones that are already processed and sent to GL.
So, system is trying to adjust the existing expenditure item id: 1234 to new burden cost 120$ and it is erroring out for some other reasons. We dont want system to recalculate past expenditure item ids.
I already checked the effective dates of the burden schedule and it starts from Feb 1 2014 so a tranaction from Jan 2014 should not be recalculated. Can anyone help here ?