Question on Oracle Burden schedule

edited Apr 11, 2014 12:13PM in Projects - EBS (MOSC) 6 commentsAnswered

We use burden schedules for cost+ projects. But we have a problem when updating existing burden rates.

Demostration:

Expenditure item id : 1234

Expenditure date : Jan 2014

Expenditure status : posted to GL

raw cost : 100 $

Burden %: 15%

Burdened cost : 115 $

On Feb 1 2014, when I change the burden % to 20% , then all expenditure item ids are recalculated including the ones that are already processed and sent to GL.

So, system is trying to adjust the existing expenditure item id: 1234 to new burden cost 120$ and it is erroring out for some other reasons. We dont want system to recalculate past expenditure item ids.

I already checked the effective dates of the burden schedule and it starts from Feb 1 2014 so a tranaction from Jan 2014 should not be recalculated. Can anyone help here ?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center