Hi,
For Lean Manufacturing setup, I have done the following steps
1. Master Routing setup done in P3009 Manufacturing constants (enabled the check box of Master Routings)
2. Created Item Number as Master Routing and Parent in P4101 for this exercise
3. In P4104, Set Cross Reference Type Code as MR and selected Item number as Parent with effective date also.
4. I have created a work center R-103, whose work center type as 2 (Lean Mfg. work center)
5. While attaching the work center R-103 to the Item number Parent, I am getting an error as Invalid work center. Check Work Center Type Flag
Can I get some suggestion to overcome this issue?