MRP generation does not include new message of WO plan entered manually

edited May 1, 2014 4:04PM in Manufacturing - JDE1 (MOSC) 2 commentsAnswered

Why does MRP (R3482) generation does not include new message of Plan WO that is entered manually by user ?

Steps :

1.  Enter forecast for item FG

2.  Enter Sales order for Item FG

3.  Run MPS generation for Item FG with planning rule C

4.  Check MPS messages - plan WO orders created for item FG

5.  However, planner sometimes want to add plan WO manually in the MPS messages (these are adhoc planning)

6.  Run MRP generation for raw materials

7.  Check MRP messages - plan PO does not include manually entered plan WO in MPS messages in step 5.

Is this std JDE planning logic or there is work around to get MRP calculated with plan manual MPS message ?

Howdy, Stranger!

Log In

To view full details, sign in to My Oracle Support Community.

Register

Don't have a My Oracle Support Community account? Click here to get started.

Category Leaderboard

Top contributors this month

New to My Oracle Support Community? Visit our Welcome Center

MOSC Help Center